The Use of Portfolio Management for Strategic Alignment – A Survey with Brazilian Companies

Autores

DOI:

https://doi.org/10.4301/S1807-1775202017004

Resumo

The number of organizations that use the Project Portfolio Management - PPM has increased considerably worldwide, as it provides an approach to the coordinated management of the components portfolio, aiming to achieve the strategies of organizations. The objective of this work was, thru a quantitative research, presents Brazilian organizations use of PPM as a mechanism to promote alignment with the strategic management. The results obtained in this research were compared with the data results obtained in PMSurvey.org´s 2012 research. A survey submitted for 56 Brazilian public and private companies was used for this study to identify project´s portfolio alignment with strategic goals and objectives.

Biografias Autor

Tomas Roberto Orlandi, Universidade de Brasília - UNB

Doutor em Ciências da Informação pela UnB - Universidade de Brasília / FCI - Faculdade de Ciências da Informação, atuando como membro do grupo de pesquisa R.E.G.I.I.M.E.N.T.O. - Arquitetura da Informação, Linguística Computacional e Multimodalidade, Mídias e Interatividade, Mestre em Gestão do Conhecimento e da Tecnologia da Informação pela Universidade Católica de Brasília (2002), Especialista em Governança de TI pela Universidade de Brasília - UNB (2007), Especialista em Engenharia de Software pela Universidade Católica de Brasília (1990) e graduação em Tecnólogo em Processamento de Dados pela Universidade Católica de Brasília (1985). Analista de Sistemas Sênior na Empresa Brasileira de Correios - ECT, assessor da Vice-presidência de Tecnologia - VITEC. Professor de graduação nas áreas de análise de sistemas e modelagem de dados. Professor de pós-graduação nas áreas de Gerenciamento de Projetos, BSC voltado para TI e Engenharia de Software. Ministra cursos e palestras em várias instituições acadêmicas e empresarias, públicas e privadas.

Fernando Santos Dantas, Universidade Católica de Brasília - UCB

Experiência de mais de 22 anos em organizações e Instituições Universitárias, exercendo as funções de Presidente, Diretor Administrativo/Financeiro, Coordenador de Projetos, Gestor de Incubadora e Mentor de Startups, Coordenador de Cursos de Graduação e Professor Universitário, participando como responsável da reestruturação e profissionalização da gestão das empresas. Mestre em Gestão do Conhecimento e da TI pela Universidade Católica de Brasília - UCB; Administrador com MBA em Gerenciamento de Projetos.

João Souza Neto, Universidade Católica de Brasília - UCB

Doutor em Engenharia Elétrica pela UNB. Mestre em Engenharia Eletrônica pelo Philips International Institute da Holanda. Engenheiro Eletricista com ênfase em Eletrônica, formado pela UERJ. Professor do Mestrado em Governança, Tecnologia e Inovação, da Universidade Católica de Brasília. Membro fundador e Vice-Presidente do Capítulo Brasília da ISACA. Detentor da Medalha do Mérito Eleitoral do TRE-DF. . Currículo: https://www.linkedin.com/in/souzaneto/

Referências

ARCHER, N.; GHASEMZADEH, F. An integrated framework for project portfolio selection. International Journal of Project Management, 17(4), 207–216, 1999.

ARCHIBALD, R.D. Managing high-techonogy programs and project. 2. ed. New York: John Wiley & Sons, 1992.

ARTTO, K.A.; DIETRICH, P.H. Strategic business management through multiple projects. In: MORRIS, P W. G.; PINTO, Jeffrey K. The Wiley guide to project program & portfolio management. New Jersey: John Wiley & Sons Inc., 2007. Cap 1, p. 1-33.

_______; MARTINSUO, M.; DIETRICH, P. H.; KUJALA, J. Project strategy: strategy types and their contents in innovation projects. International Journal of Managing Projects in Business. v.1, n.1, p.49-70. 2008.

ARTTO, K. A.; DIETRICH, P. H. Strategic business management through multiple projects. In: MORRIS, Peter W. G.; PINTO, Jeffrey K. The Wiley guide to project program & portfolio management. New Jersey: John Wiley & Sons Inc., 2007.

BUYS, A. J.; STANDER, M. J. Linking Projects to Business Strategy through Project Portfolio Management. South African Journal of Industrial Engineering, v. 21, 2010.

CABANIS-BREWIN, J. Best practices for aligning projects to corporate strategy. In: Proceedings of the PMI Research Conference, 2006, Seattle. Proceedings P.1-8: PMI, 2006..

CARVALHO, M.M.; RABECHINI JÚNIOR. Construindo competências para gerenciar projetos. 2. Ed. São Paulo: Atlas, 2007. 317 p.

_______. Valor em projetos: uma abordagem contingencial. No prelo, 2010.

_______. Fundamentos em gestão de projetos: construindo competências para gerenciar projetos – 3. Ed. – São Paulo: Atlas, 2011.

CLELAND, D. I.; IRELAND, L. R. Gerência de projetos. Rio de Janeiro: Reichmann & Affonso, 2002.

COOPER, R. G.; EDGETT, S. J.; KLEINSCHMIDT, E. J. Porfolio management for new products. Cambridge, Mass. Perseus, 2001.

COSTA, H. Seleção de Portfólio de Projetos. PMO: escritório de projetos, programas e portfólio na prática / André Barcaui, (org.). -- RJ: Brasport, 2012.

DINSMORE, P.C; CAVALIERI, A. Como se tornar um profissional em gerenciamento de projetos: livro-base de preparação para certificação PMP – Project Management Professional. Rio de Janeiro: Qualitymark, 2005.

DUQUE, W.S.; PELISSARI, A. S. Proposição de modelo entre gerenciamento de projetos e gestão estratégica: alinhamento de Processos para a Realização de Objetivos Organizacionais.34 ENCONTRO DA ANPAD, RJ, 2010.

DYE, L. D.; PENNYPACKER, J. S. Project portfólio management: selecting and prioritizing projects for competitive advantage. West Chester: Center for Business Practices, 1999.

KAPLAN, R. S.; NORTON, D. Mapas Estratégicos: Balanced Scorecard. 1. Ed. –– São Paulo: Atlas, 2004.

KERZNER, H.. Project Management Best Practices: Achieving Global Excellence. New Jersey: John Wiley & Sons, 2006.

KILLEN, C.P., HUNT, R.A., KLEINSCHMIDT, E. J. Managing the New Product Development Project Portfolio: a review of the literature and Empirical evidence. In: PICMET, pp. 1864 – 1874, Portland, Oregon, 2007.

KRAUSE, W. Governança Corporativa e o PMO. PMO: escritório de projetos, programas e portfólio na prática, André Barcaui,(org.). Rio de Janeiro: Brasport, 2012.

LEVINE, H. A. Project Portfolio Management: A practical guide to selection project selection with business strategy. Project Management Journal, vol. 19(5), pp. 14, 1988.

MARKOWITZ, H. Portfolio Selection. The Jounal of Finance, v. 7, pp. 77-91, 1952.

MAXIMIANO, A.C.A. Administração de projetos: como transformar ideias em resultados. 4. Ed. – São Paulo: Atlas, 2010.

McDONAUGH III, E. F.; SPITAL, F. Managing Project Portfolios: Not theory but day-to-day management policies and actions will determine the success of a new product development effort, this study shows. Research Technology Management, v. 46, n. 3, p. 40-46, 2003.

MILOSEVIC D. Z.; SRIVANNABOON, S. A theoretical framework for aligning Project management with business strategy. P M Journal, v. 37, n. 3, p. 98-110, 2006.

MINTZBERG, H., AHLSTRAND, B., LAMPEL, J. Safári de estratégia: um roteiro pela selva do planejamento estratégico. 2. Ed. – POA: Bookman, 2010.

MOECKEL, A. Sistematização da gestão de portfólio na fase de planejamento estratégico de produtos. 2009. 219 f. Tese (Doutorado) - Curso de Engenharia Mecânica, Universidade Federal de Santa Catarina, Florianópolis, SC, 2009.

MORRIS, P.; JAMIESON, A. Translating corporate strategy into project strategy: realizing corporate strategy through project management. PMI publications, 2004.

_______. Moving from corporate strategy to project strategy. PM Journal. v.36, n.4, p.5-18. 2005.

OSAMA, A. Multi-Attribute Strategy and Performance Archtectures in R&D - The Case of the Balanced Scorecard. 2006. Pardee RAND Graduate School, 2006.

PADOVANI, M.; CARVALHO, M. M.; MUSCAT, A. R. N. Ajuste e balanceamento do portfólio de projetos: o caso de uma empresa do setor químico. Produção. USP, São Paulo, SP, 2011. Recebido 05/07/2009; Aceito 25/07/2011.

PATANAKUL, P; SHENHAR, A J.; MILOSEVIC, D. Why different projects need different strategies. In: SHENHAR, A.J.; MILOSEVIC, D.; DVIR, D. THAMHAIN, H. Linking project management to business strategy. Newton Square: Project Management Institute Publications, 2007. Cap. 8, p. 143-160.

PROJECT MANAGEMENT INSTITUTE. The Guide to the Project Management Body of Knowledge, Newtown Square 4. ed. Pennsylvania: PMI Inc., 2008a.

PROJECT MANAGEMENT INSTITUTE. The Standart for Portfolio Management, Newtown Square 2. ed. Pennsylvania: PMI Inc., 2008b.

PMSURVEY.ORG. Project Management Office (PMO) – Um Panorama da Próxima Geração. 2012.

RABECHINI JÚNIOR, R. Competências e maturidade em gestão de projetos: uma perspectiva estruturada. São Paulo: Annablume; Fapesp, 2005.

_______; PESSÔA, M.S.P. Um modelo estruturado de competências e maturidade em gerenciamento de projetos. Revista Produção, São Paulo, v. 15, n. 1, p.34-43, 2005.

_______; MAXIMIANO, A.C.A; MARTINS, V A. A adoção de gerenciamento de portfólio com uma alternativa gerencial: o caso de uma empresa prestadora de serviço de interconexão eletrônica. Revista Produção, São Paulo, v. 15, n. 3, p. 416-433, 2005.

_______; CARVALHO, M.M.; LAURINDO, F. J. B. Fatores críticos para implementação de gerenciamento por projetos: o caso de uma organização de pesquisa. Revista Produção, São Paulo, v. 12, n. 2, p. 28-41, 2002.

RAO, R. Connecting organization strategy to projects: the missing link. In: 2007 PMI GLOBAL CONGRESS PROCEDINGS, 2007, Hong Kong. Paper. Newtown Square: Project Management Institute, 2007.

REZENDE, D. A. Alinhamento do planejamento estratégico da tecnologia da informação ao planejamento empresarial: proposta de um modelo e verificação da prática em grandes empresas brasileiras. 278 f. Tese (Doutorado em Engenharia de Produção) – UFSC – Engenharia de Produção, 2002.

RIBEIRO, W. L. Proposta de um modelo para a implantação de um escritório de projetos estratégico de TI em empresas de telecomunicações. Dissertação (Mestrado) – Mestrado - Gestão do Conhecimento e da TI, UCB, Brasília, DF, 2007.

ROCHA, M.H.P.; NEGREIROS, L.A. Alinhamento estratégico e o gerenciamento de portfólio de projetos nas organizações. V Congresso Nacional de Excelência em Gestão. Gestão do Conhecimento para a Sustentabilidade. Niterói, 2009.

SANTOS, M.C. O escritório de gerenciamento de projetos no planejamento estratégico e orçamentário: um estudo de caso na indústria de mídia sob o enfoque da cibernética. 2007. Dissertação (Mestrado) - Curso de Engenharia Naval e Oceânica, Escola Politécnica de São Paulo; USP, São Paulo, 2007.

SHENHAR, J. A.; et al.. Linking Project Management to Business Strategy. Newton Square, PA, US: Project Management Institute, 2007. (19-55).

SHENHAR, A.; STEFANOVIC, J. Does strategic alignment contribute to business success Project success: a multidimensional strategic concept? In: SHENHAR, AJ.; MILOSEVIC, D; DVIR, D. THAMHAIN, H. Linking project management to business strategy. Newton Square: PMI Publications, 2007. Cap. 12, p. 213-232.

SRIVANNABOON, S. Linking Project Managemente With Business Strategy. Project Management Jounal, p. 88-96, Pennsylvania, 2006.

TAVARES, M. C. Planejamento Estratégico: a opção entre o sucesso e o fracasso empresarial. São Paulo: Harbra, 1991.

TERRA, J. C.; et al.. Gestão de Portfólio: o desafio do alinhamento estratégico. Biblioteca: Terra Fórum Consultores. Disponível em: Acesso:02/03/12.

VALERIANO, D. L. Gerenciamento estratégico e administração por projetos. São Paulo: Makron Books, 2001.

WRIGHT, P. L., KROLL, M.J., PARNELL, John. Administração estratégica: conceitos: tradução Celson A. Rimoli, Lenita R. Esteves. 1. Ed. – 12. Reimpr. – São Paulo: Atlas, 2011.

Downloads

Publicado

2021-03-11

Como Citar

Orlandi, T. R., Dantas, F. S., & Neto, J. S. (2021). The Use of Portfolio Management for Strategic Alignment – A Survey with Brazilian Companies. Journal of Information Systems and Technology Management, 17. https://doi.org/10.4301/S1807-1775202017004

Edição

Secção

Articles